Padma Bridge work to be completed by June 2021

Staff Correspondent
17 October 2019, Thu
Published: 06:48

Padma Bridge work to be completed by June 2021

Awami League general secretary, road transport and bridge Minister Obaidul Quader said the construction work on the Padma Bridge will be completed by June, 2021.

Quader said this while talking to reporters at the Visitors’ Centre of Service Area-1 of the Padma Bridge here in the afternoon on Thursday (Oct 17).

Obaidul Quader informed that more than 84 percent construction work of the bridge has been completed so far. The overall progress of the bridge work is 74 percent right now while the financial progress is 75.84 percent.

He said that Padma River is very unpredictable. Sometimes it becomes difficult to place spans on piers. So, it’s not possible to complete the construction work within the scheduled time,

Obaidul told that the driving work on all the piles of the main bridge has been completed in addition to constructing 32 out of 42 piers and completion of 63 - percent river training work. Construction work on connecting roads has also been completed. And a dairy farm of Bangladesh Army will be set up on a land which has remained fallow since its acquisition.